Answer:
Revenue earned: $36,853
Explanation:
Percentage of completion method seeks to calculate the revenue earned by multiplying the total project revenue to the ratio of cost incurred to total cost estimated cost of the project. This is simplified by below calculation:
Revenue earned = Total project revenue * (Cost incurred / Total estimated project cost)
Total estimated project cost = Cost incurred + Estimated cost to complete the project
Total estimated project cost: 11,210 + 28,205 = 39,415
Revenue earned = 51,500 * (28,205 / 39,415)
Revenue earned = $36,853