Answer:
3,078.9
Explanation:
Given that,
customer orders $102.35 per customer order
Assembling products $2.65 per assembly hour
Setting up batches $54.31 per batch
Total cost:
= Customer order + Assembly hour + Batch
= [102.35 × 4] + [2.65 × 495] + [54.31 × 25]
= 409.4 + 1,311.75 + 1,357.75
= 3,078.9
Therefore, the overhead cost that would be assigned to Product F76D using the activity-based costing system is 3,078.9.