Respuesta :
Answer:
Crossover rate is the rate at which the NPV of two projects are equal is called crossover rate. The NPV of any project is computed by the following formula:
NPV = CF1/(1 + r)^1 + CF2/(1 + r)^2 + CF3/(1 + r)^3 − Initial Investment
Now for Project A and B, we have following equations:
NPV1 = CF1/(1 + r)^1 + CF2/(1 + r)^2 + CF3/(1 + r)^3 − A
NPV2 = CF1/(1 + r)^1 + CF2/(1 + r)^2 + CF3/(1 + r)^3 + CF4/(1 + r)^4 − B
By putting values we have:
NPV1 = 49400/(1 + r)^1 + 27200/(1 + r)^2 + 24500/(1 + r)^3 − 50,000
And
NPV2 = 18500/(1 + r)^1 + 18500/(1 + r)^2 + 18500/(1 + r)^3 + 18500/(1 + r)^4 − 50,000
Now at crossover rate (a point of intersection of equation of project A and project B), the NPV of project A equals the NPV of project B. This means
NPV equation of project A = NPV equation of project B
49400/(1 + r)^1 + 27200/(1 + r)^2 + 24500/(1 + r)^3 − 50,000 = 18500/(1 + r)^1 + 18500/(1 + r)^2 + 18500/(1 + r)^3 + 18500/(1 + r)^4 − 50,000
Adding +50,000 on both sides of equal sign will cancel out the -50,000 on both sides. Now the equation is as under
49400/(1 + r)^1 + 27200/(1 + r)^2 + 24500/(1 + r)^3 = 18500/(1 + r)^1 + 18500/(1 + r)^2 + 18500/(1 + r)^3 + 18500/(1 + r)^4
Moving left hand side to right hand side will change the signs
0 = 18500/(1 + r)^1 + 18500/(1 + r)^2 + 18500/(1 + r)^3 + 18500/(1 + r)^4 - 49400/(1 + r)^1 - 27200/(1 + r)^2 - 24500/(1 + r)^3
Now rearranging according to the denominator,
0 = [18500/(1 + r)^1 - 49400/(1 + r)^1 ] + [18500/(1 + r)^2 - 27200/(1 + r)^2] + [18500/(1 + r)^3 - 24500/(1 + r)^3] + 18500/(1 + r)^4
Now taking denominators common from brackets we have:
0 = [18500 - 49400]/(1 + r)^1 + [18500 - 27200]/(1 + r)^2 + [18500 - 24500]/(1 + r)^3 + 18500/(1 + r)^4
Adding amounts in the brackets we have:
0 = -30,900/(1 + r)^1 - 8,700/(1 + r)^2 - 6,000/(1 + r)^3 + 18500/(1 + r)^4
Multiplying by Minus 1 on both sides we have:
0 = 30,900/(1 + r)^1 + 8,700/(1 + r)^2 + 6,000/(1 + r)^3 - 18500/(1 + r)^4
Now the equation we have can be used for finding "R" by using IRR method.
Using Internal Rate of Return method:
Year Cash flow Lower rate@30% NPV at lower rate
1 30,900 0.769 23769
2 8,700 0.592 5148
3 6,000 0.455 2731
4 (18,500) 0.350 (6477)
Total 25171
Now using higher rate we will find NPV at higher rate:
Year Cash flow Higher rate@32% NPV at higher rate
1 30,900 0.758 23409
2 8,700 0.574 4993
3 6,000 0.435 2609
4 (18,500) 0.330 (6094)
Total 24917
IRR equation= Lower rate + [NPV at lower rate/(NPV at lower rate - NPV at higher rate)] * (Higher rate -lower rate)
Now putting values in the IRR equation we can find the crossover rate:
Crossover rate= 30% + [25171/(25171-24917)]*(32-30)%
Crossover rate = 30% + 1.98%= Almost 32%