a. Average time of producing the 1st batch (a) = 110,000 hours
Defined cummulative output (x) = 8 satellites
b= Log of learning curve %/Log 2
Y = axb
Y = 110,000(8)log 0.8/log 2
Y = 110,000 x 0.512
Y = 56,320 hours
b. The total labour hours for the whole project
= 56,320 hours x 8 satellites
= 450,560 hours
Explanation:
Improvement curve is a function of average time of producing the 1st batch of satellites multiplied by the defined output raised to power log of learning curve % divided by log 2.
The total labour hours for the whole project equals average time of producing 8 satellites multiplied by 8 satellites.