Jaime has 5 over 11 spaceof a project completed while Tim has finished 7 over 13 spaceof the same project.

a. Who has completed the greater amount of work?

b. How much of the project have they completed together? Show your work.

Respuesta :

Answer:

Part a) Tim has completed the greater amount of work

Part b) They have completed together [tex]\frac{142}{143}[/tex] of the project or [tex]99.3\%[/tex] of the project

Step-by-step explanation:

Part a) Who has completed the greater amount of work?

we have

Jaime has 5/11 of a project completed

Tim has 7/13 of a project completed  

Multiply 5/11 by 13/13 and 7/13 by 11/11

so

Jaime ---> [tex]\frac{5}{11}(\frac{13}{13})=\frac{65}{143}[/tex]

Tim ---> [tex]\frac{7}{13}(\frac{11}{11})=\frac{77}{143}[/tex]

Remember that

When fractions have the same denominator, the larger fraction is the one with the larger numerator  

[tex]\frac{77}{143} >\frac{65}{143}[/tex]

therefore

Tim has completed the greater amount of work

Part b)  How much of the project have they completed together?

we have that

Jaime has 65/143 of a project completed  

Tim has 77/143 of a project completed  

Sum the fraction of the project completed by Jaime plus the fraction of the project completed by Tim

[tex]\frac{65}{143}+\frac{77}{143}=\frac{142}{143}[/tex]

Convert to percentage

Multiply by 100

[tex]\frac{142}{143}(100)=99.3\%[/tex]