Monica, a project manager at a software firm, learns during a status report meeting that a difference exists between the baseline scope and the actual project performance. What does Monica need to do next?
1. Propose a schedule change
2. Analyze the variance
3. Implement a scope change
4. Expand the project scope

Respuesta :

Answer: 2. Analyze the variance

Explanation:

As a project manager, Monica needs to first understand the differences which exists between the baseline scope and actual project performance. She needs to analyse the fact or quality of the differences and inconsistency that exists, in order to prevent potential disagreement or conflicts with the clients or company.