Answer:
Budgeted cost for July will be equal to $5628
So option (d) will be the correct option
Explanation :
We have given Budgets production for July = 280 units
Each unit requires 1.5 hours of direct labor
Total Direct Labor Required = 280×1.5 = 420 hours
The direct labor rate = $13.40 per hour
Therefore, the Budgeted direct labor cost for July = 420 Hours × $ 13.40 = $ 5628.
So the budgeted cost for July will be equal to $5628
So option (D) will be the correct option