Respuesta :
Answer:
12. 21 % ; 41.98 % and 45.80 % as below
Explanation:
Total cost for the stadium is
labor $ $16,000
leasing the parking fee $55,000
Busing to and from $60,000
Total cost $131,000
Percentage per item
1. labor = 16000/131000 x 100
=12.21 percent
2.leasing parking space= 55000/131000 x 100
=41. 98 percent
3.Parking space= 60,000/131000x100
=45.80 percent