Answer:
30
Step-by-step explanation:
16 days is 16/80 = 1/5 the time for 6 builders, so the number of builders required is 1/(1/5) = 5 times that:
5 × 6 builders = 30 builders
Answer:
[tex]\displaystyle 30[/tex]
Step-by-step explanation:
[tex]\displaystyle [\frac{80}{16}][6] = [5][6] = 30[/tex]