Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, the company planned for activity of 6,200 machine-hours, but the actual level of activity was 6,150 machine-hours. The actual manufacturing overhead for the month was $373,630. 23.The manufacturing overhead in the planning budget for March would be closest to:
A.$373,630
B.$371,650
C.$376,668
D.$374,300