Respuesta :
Answer:
D. Timeline of the project may change
Explanation:
In a project, activities tend to have a dependency relationship on one another. Delay in one activity may result in project schedule slippage if it happens to be on the critical path. As a result, when a project manager receives a communication about one of the tasks getting delayed- namely, the report being late , it implies that the timeline of the project may possibly change.
Answer: D (The timeline of the project may change)
Explanation: It is D because they turned the report late which can affect the time in which the project can be finished. It’s not the others because it only affects the time not the pricing or resource or scope.