Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 20 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. If she were to order 80 pounds of pepperoni at a time, what would be the length of an order cycle?(A) 4 days(B) 5 days(C) 3 days(D) 0 days(E) .25 days

Respuesta :

Answer:

Option (A) is correct.

Explanation:

Given that,

Order costs for pepperoni = $10.00 per order

Carrying costs = 4 cents per pound per day

Lead time for each order = 3 days

Pepperoni itself costs = $3.00 per pound

Total Order = 80 pounds of pepperoni

Demand rate = 20

Total ordering cost = Total order × cost per order

                                = 80 × $10

                                = $800

Length of an order cycle:

[tex]=\frac{Order\ quantity}{Demand\ rate}[/tex]

[tex]=\frac{80}{20}[/tex]

= 4 days