Red Builders agrees to construct a new building for Blue Co. for a total contract price of $6,000,000. The estimated construction costs at inception was $4,000,000. The construction project was completed after two years. Below are the actual costs for years 1 and 2: DescriptionCumulative Year 1Year 2Cost incurred to date1,200,0002,500,000Estimated additional costs to complete3,600,0002,100,000Billings1,050,0002,300,000Cash Collections1,000,0001,900,000 Red has determined that this contract qualifies for revenue recognition over time (as opposed to upon completion). As a result, Red Builders should have recognized profit at the end of year 1 in the amount of:

Respuesta :

Answer: $300,000

Explanation:

Total expected costs = cost incurred to date + estimated cost to complete

                                   = 1,200,000 + 3,600,000

                                   = 4,800,000

[tex]Percentage of completion=\frac{Cost\ incurred\ to\ date}{Total\ expected\ cost}\times 100[/tex]

[tex]Percentage of completion=\frac{1,200,000}{4,800,000}\times 100[/tex]

                                                 = 0.25

                                                 = 25%

Profit = contract revenue - Total expected costs

         = $6,000,000 - 4,800,000

         = $1,200,000

Cumulative gross profit = Profit × Percentage of completion

                                       = $1,200,000 × 0.25

                                       = $300,000

Therefore, Red Builders should have recognized profit at the end of year 1 in the amount of $300,000.