Answer:
The manufactured overhead was under-estimated.
Explanation:
Giving the following information:
The actual manufacturing overhead costs incurred were $515,000.
Estimated Manufacturing overhead was $500,000.
Overhead allocation is the distribution of indirect costs to produced goods. When the administration has undervalued and under-funded the amount of money needed for non-production costs, they have under-allocated overhead.
Over applied manufacturing overhead:
Applied overhead>Actual overhead
Under applied manufacturing overhead:
Applied overhead<Actual overhead
In this exercise:
Actual manufacturing overhead - Estimated Manufacturing overhead= 515000- 500000= 15000
The manufactured overhead was under-estimated.