Respuesta :
Answer:
The overhead for the year was $130,075
Explanation:
GIVEN INFORMATION -
ESTIMATED ACTUAL
Manufacturing overhead $132,440 $128,600
Machine hours 2800 2750
Here for calculating the overhead for the year we will use the following formula =
\frac{Estimated Manufacturing Overhead}{Estiamted Machine Hours}\times Actual Machine Hours
= \frac{\$132,440}{2800}\times 2750
\$47.3\times 2750 = \$130,075
Therefore the overhead for the year was $130,075
Answer:
The overhead for the year was: $130,075.
Explanation:
We have the following formula to determine overhead for the year:
+ Overhead for the year = Predetermined overhead rate ($ per machine hour) x Actual machine hours;
in which:
+ Predetermined overhead rate = Estimated manufacturing overhead / Estimated machine-hours = 132,440 / 2,800 = $47.3/machine hour.
+ Actual machine hours is given at 2,750 hours.
=> Overhead for the year = Predetermined overhead rate ($ per machine hour) x Actual machine hours = 47.3 x 2,750 = $130,075.
So, the answer is $130,075.