The animal shelter is building cages for 26 dogs and 34 cats.
26 + 34 = 60
It needs to build 60 cages.
The first crew builds 1 cage in 1 hour. Rate: 1 cage/hour
The second crew builds 1 cage in 2 hours, or 1/2 cage in 1 hour. Rate: 1/2 cage/hour
They work together for x hours and build all 60 cages.
In x hours, the first crew builds 1 cage/hour * x hours = x cages.
In x hours, the second crew builds 1/2 cage/hour * x hours = 1/2 x cages.
Combined, they build 60 cages.
x + 1/2 x = 60
x + 0.5x = 60
1.5x = 60
x = 40
Answer: It will take 40 hours.
Check: In 40 hours, the first crew builds 40 cages.
In 40 hours, the second crew builds 20 cages.
40 + 20 = 60
In 40 hours, the two crews build 60 cages.
Our answer above is correct.
All together, the shelter needs (26 + 34) = 60 new cages built.
Crew #1 builds a cage in 1 hour. They finish 1 cage/hour.
Crew #2 builds a cage in 2 hours. They finish 1/2 cage/hour.
When both crews work, they finish (1 + 1/2) = 1.5 cage/hour.
To build 60 cages, it will take them
(60 cages) / (1.5 cage/hour) =
(60 cages) ÷ (1.5 cage/hour) =
(60 cages) x (hour / 1.5 cage) =
(60 cage-hour) / (1.5 cage) =
(60 / 1.5) (cage·hour/cage) =
40 hours