You are the project manager of the Al Project for a new building. Your BAC is $500,000. You have spent $225,000 of your budget. You are now 40 percent done with the project, though your plan called for you to be 45 percent done with the work at this time. What is your CPI?
a) 0.90
b) 1.12
c) 0.80
d) 1.25