averyrogerss7078 averyrogerss7078 13-03-2024 Computers and Technology contestada There are two main types of Program Evaluation Review Technique (PERT) charts, including which of the following? A. NOA (Non-Overlap Activities) B. Action on arrow (AOA) C. Action on node (AON) D. Gantt Chart