Match the definitions to the three different methods of earth embankment construction. Group of answer choices:
Method A Earth embankments shall be compacted in successive horizontal layers not exceeding 2' in thickness.
Method B Under this method each layer of the top 2 feet of embankments shall be compacted to 95 percent and each layer of embankments below the top 2 feet shall be compacted to 90 percent of the maximum density.
Method C Under this method each layer of the entire embankment shall be compacted to 95 percent of the maximum density as determined by compaction control tests.
A) Method A: Standard compaction, Method B: Modified compaction, Method C: Proctor compaction
B) Method A: Proctor compaction, Method B: Modified compaction, Method C: Standard compaction
C) Method A: Modified compaction, Method B: Proctor compaction, Method C: Standard compaction
D) Method A: Standard compaction, Method B: Proctor compaction, Method C: Modified compaction