P alone can complete the work in 20 days and Q alone can complete the work 30 days. They work alternatively for 4 days. After 4 days, they work together to complete the half of the work. Remaining work is completed by P. In completing the work, total days P worked is-
1. 27 days
2. 21 days
3. 18 days
4. 16 days