In developing and setting up an Arranged Interchange, which of the following would transition the Arranged Interchange to the Confirmed Interchange status?
A) The TSP's and BA's listed on the Tag have approved the Tag.
B) The BA's and TSP's listed on the Tag have enter the information in their EMS
C) All PSE's listed on the Tag have provided approval.
D) All RC's listed on the tag have provided approval.