JorgieX6061 JorgieX6061 15-02-2024 Computers and Technology contestada ActivityPredecessorTime(weeks) A--8 BA6 C--4 DC9 EA11 FB3 GD, E,F1 Using Table 7.4, what is the largest amount of slack in the project? Select one: A. four weeks B. six weeks C. nine weeks D. eleven weeks