Activity D on a CPM network has predecessors B and C and has a successor F. D has a duration of 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following statements is true?
a. D is the critical path
b. D's late start is 26
c. D's earliest start is 12
d. D's latest finish is 20