Woody8595 Woody8595 13-02-2024 Engineering contestada The owner adds two additional levels in a 10-story building. The contractor's claim is based on: a. Force majeure. b. Differing site conditions. c. Design errors/omissions. d. Unusual weather conditions. e. Changes in owner's requirements.