Under a cost-reimbursement, time and materials, or labor hour contract, which one of the following statements is FALSE?
1) The contractor is reimbursed for allowable costs incurred
2) The contractor is paid a fee for profit
3) The contractor is responsible for managing the project
4) The contractor is not required to submit cost or pricing data