Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

a. More work has been done than planned
b. There is not enough information to draw a conclusion
c. The same amount of work has been done than planned
d. Less work has been done than planned
e. The project has cost less than planned