The XYZ company produces three products using mixed assembly on a line which is
operated 8 hours per day for 250 days per year. The annual demand forecast is as follows:
Product Forecast
A 10500
B 6500
C 3250
For a firm wanting to have a daily schedule in which there is a single setup per product, the
daily schedule is
a. A(50), B(27), C(15) one time per day
b. A(42), B(26), C(13) one time per day
c. A(10), B(6), C(3) five times per day
d. A(20), B(15), C(5) two times per day
e. A(14), B(10), C(1) one time per day