you are in the process of estimating the activity durations for the various activities contained in the scope baseline for a large project being undertaken by your organization. you have an activity that will most likely take eight days to complete. it has been determined that the activity has a best case scenario of being completed in four days and a worst case scenario of taking 18 days. which duration will you record for this activity using pert?