you have been assigned to replace a project manager at the beginning of project execution. you are in the process of reviewing the activities completed by the previous project manager. you determine that the previous project manager has completed the schedule and budget. the previous project manager also determined the quality specifications and began checking the products from the project. after confirming that a process improvement plan was created and roles and responsibilities of project team members have been identified, what should you do next?