The risk management team of a software project has decided that due to the lack of adequate talent in your company, development of a specific part of the system is under high risk, so they have decided to outsource it. This is an example of which of the following?
a. Risk avoidance
b. Risk mitigation
c. Risk acceptance
d. Risk transfer