zackasanford4255 zackasanford4255 14-09-2022 Business contestada During a sprint planning meeting, the agile teams require to deliver stories 1, 2, 3 and 4 having estimates of 10, 12, 14 and 6 story points. However, the team was able to complete stories 1, 2, 30% of 3 and 50% of 4. What is the team velocity?