QUESTION 3 The work processing time and due dates are given in the following table. The firm wants to prepare the sequence of processing according to EDD rules. Jobs were assigned a letter in the order they arrived. Calculate measurement of effectiveness for EDD rule. (C3) Answer: JOB SEQUENCE CX-01 BR-02 RG-05 DE-06 SY-11 TOTAL JOB BR-02 CX-01 DE-06 RG-05 SY-11 iv. Utilization JOB WORK (PROCESSING)TIME (DAYS) JOB WORK (PROCESSING)TIME 6 10 7 12 13 48 ii. Average number of jobs in the system iii. Average job lateness 10 6 12 7 13 Answer: Calculate measurement of effectiveness for EDD rule (C3). i. Average completion time FLOW TIME JOB DUE DATE (DAYS) 12 10 22 19 27 JOB DUE DATE 10 12 19 22 27 (6 marks) JOB LATENESS Scanned with CamScanner